Hi All!
My project is about a 6 kV, 10.5 MW diesel powered generator, inside a petrol chemistry faciliy. The vendor of the diesel-generator set recommend a switchable grouded neutral point, with 50 ohms resistor. The power plant is in an existing facility, but in a new building, on a clear space. The generator will be connected to the 6/20/120kV substation (power company). The secondary LV energy will be provided from the facility power system, using NYCWY 4x240/25 cables, so the neutral connection is assured. The MV cables between the generator and the power company substation will be N2XS(F)2Y 3x300/25. Could anybody answer to my questions:
-why the neutral switch is required?
-what are the recommendations for the new grounding system: grounding net around the generator building is enough (the generator's neutral point connected to it), or earthing well is reuired too (the management of the facility wants a well).
Thank you for your answers!
My project is about a 6 kV, 10.5 MW diesel powered generator, inside a petrol chemistry faciliy. The vendor of the diesel-generator set recommend a switchable grouded neutral point, with 50 ohms resistor. The power plant is in an existing facility, but in a new building, on a clear space. The generator will be connected to the 6/20/120kV substation (power company). The secondary LV energy will be provided from the facility power system, using NYCWY 4x240/25 cables, so the neutral connection is assured. The MV cables between the generator and the power company substation will be N2XS(F)2Y 3x300/25. Could anybody answer to my questions:
-why the neutral switch is required?
-what are the recommendations for the new grounding system: grounding net around the generator building is enough (the generator's neutral point connected to it), or earthing well is reuired too (the management of the facility wants a well).
Thank you for your answers!