Hello.
I almost started my PV installation but I have some concerns about the cable connecting the inverter with the meter. Currently, the cable is 2.5mm.
The instruction recommends 10 AWG which translates into a 5.3 mm2 cable round it to 6mm2.
I have to route two wires. From the meter to the inverter and from the inverter to power the house. connection also at the place of the meter.
I wanted to give 5x6mm2 one wire. Two wires from the meter and two to power the house. I'm afraid of overheating the cable and hence greater failure rate.
So I put on two separate wires. One from the meter to the inverter and the other from the inverter to power the house and I have the choice:
YDYp 3x6mm2 450 / 750V cable
or
YLY cable 3x6mm2 0.6 / 1kV
I will add that sometimes I download from the network about 4.5-5.5kW 2.5kW 2kW kettle and the rest of the house 1kW.
The wire speaks because it is cheaper and easier to lay. The cable is stable. In this case, I focus only on the experience of colleagues.
I almost started my PV installation but I have some concerns about the cable connecting the inverter with the meter. Currently, the cable is 2.5mm.
The instruction recommends 10 AWG which translates into a 5.3 mm2 cable round it to 6mm2.
I have to route two wires. From the meter to the inverter and from the inverter to power the house. connection also at the place of the meter.
I wanted to give 5x6mm2 one wire. Two wires from the meter and two to power the house. I'm afraid of overheating the cable and hence greater failure rate.
So I put on two separate wires. One from the meter to the inverter and the other from the inverter to power the house and I have the choice:
YDYp 3x6mm2 450 / 750V cable
or
YLY cable 3x6mm2 0.6 / 1kV
I will add that sometimes I download from the network about 4.5-5.5kW 2.5kW 2kW kettle and the rest of the house 1kW.
The wire speaks because it is cheaper and easier to lay. The cable is stable. In this case, I focus only on the experience of colleagues.