Hello,
I wanted a broader opinion.
Well, I'm talking about the configuration where the on-grid photovoltaic installation will be made.
It will be made with funding from the commune, so I don't really have control over everything. However, I would like to be aware of the limitations resulting from the proposed solution, which is expected to appear in the spring.
The thing is that there were intermittent power outages in the area where I live. Usually lasting no more than a second, but everything was resetting. The power plant was warned and the blackouts disappeared, but this is not the first time they appear.
In addition, there are temporary outages because the network in the area is being modernized.
I would like to protect myself against long shutdowns and use a three-phase power generator with ats and AVR stabilization. Three-phase because, unfortunately, I have devices after all phases and it's hard to convert now so that the critical ones are on one phase.
In addition, I have an induction hob that needs 3 phases where with longer shutdowns I would like to use one "burner".
So I estimate that I would need about 10kW of a three-phase generator.
And here is the problem because when I was looking for aggregates with such power, they are for 5k and for 15k where the description does not show too much what the differences are. Everyone says it's great and all.
Could I ask for help in identifying a worthy investment and verifying whether my assumptions are correct. I mean, is it worth pushing into a generator with such power.
The second thing about the photovoltaics that will be. When there is no electricity in the grid, the photovoltaic does not produce anything, but when power from the generator appears, production will start. If the load is too small, there should be some communication between the photovoltaic and the generator?
Or maybe the inverter is supposed to detect the lack of consumption and turn off the photovoltaic system? If so, will every inverter be able to do this or does it have to be dedicated?
If in the future I would like to expand such a set with a UPS, does it make sense. To make it 3-phase, for example:
"UPS EMERGENCY POWER SUPPLY POWER WALKER VFI 10000 CPE 3/3 BI"
However, there must also be communication with the ATS here. Connecting the UPS to each critical device as soon as the power supply from the generator will be available in a few seconds does not make sense.
I would like to add that such a solution will certainly be expensive, so before I start digging further, I am asking for advice and opinions.
I wanted a broader opinion.
Well, I'm talking about the configuration where the on-grid photovoltaic installation will be made.
It will be made with funding from the commune, so I don't really have control over everything. However, I would like to be aware of the limitations resulting from the proposed solution, which is expected to appear in the spring.
The thing is that there were intermittent power outages in the area where I live. Usually lasting no more than a second, but everything was resetting. The power plant was warned and the blackouts disappeared, but this is not the first time they appear.
In addition, there are temporary outages because the network in the area is being modernized.
I would like to protect myself against long shutdowns and use a three-phase power generator with ats and AVR stabilization. Three-phase because, unfortunately, I have devices after all phases and it's hard to convert now so that the critical ones are on one phase.
In addition, I have an induction hob that needs 3 phases where with longer shutdowns I would like to use one "burner".
So I estimate that I would need about 10kW of a three-phase generator.
And here is the problem because when I was looking for aggregates with such power, they are for 5k and for 15k where the description does not show too much what the differences are. Everyone says it's great and all.
Could I ask for help in identifying a worthy investment and verifying whether my assumptions are correct. I mean, is it worth pushing into a generator with such power.
The second thing about the photovoltaics that will be. When there is no electricity in the grid, the photovoltaic does not produce anything, but when power from the generator appears, production will start. If the load is too small, there should be some communication between the photovoltaic and the generator?
Or maybe the inverter is supposed to detect the lack of consumption and turn off the photovoltaic system? If so, will every inverter be able to do this or does it have to be dedicated?
If in the future I would like to expand such a set with a UPS, does it make sense. To make it 3-phase, for example:
"UPS EMERGENCY POWER SUPPLY POWER WALKER VFI 10000 CPE 3/3 BI"
However, there must also be communication with the ATS here. Connecting the UPS to each critical device as soon as the power supply from the generator will be available in a few seconds does not make sense.
I would like to add that such a solution will certainly be expensive, so before I start digging further, I am asking for advice and opinions.