Hello, we operate in a remote part of East Malaysia. Our factory operates a 1.6MW steam turbine and fallback to diesel generator when required.
We have several domestic housing estates within a 10KM radius from the factory. These estate consume pure single phase loads. Lights, fans, tv, mobile phone. Very basic living. Currently, the loads are supported by diesel generator.
We are considering eliminating the remote diesel generator to save costs. One of these estates is 6KM away and the load is 7KVA all single phase. Approx 30amps if using 230volts.
Is there any issue with sizing a simple 2 core cable (proposed 2 * 35mm2 aluminium cores) and running it underground (steel tape armoured) from factory to remote estate; at factory, have a step up transformer (to 1000volts) that can convert the 1 phase load and balance it across 3 phases for supply side; and lastly a single phase step down transformer at remote estate?
Or it is only advisable to run a 3 phase cable between the 2 sites and then distribute the loads as best possible between different houses. The cost of running 2 cores single phase is of course cheaper.
If the cable is direct buried 1 foot below the ground, is there any recommend material for backfill?
Really appreciate any help.
Prashant Patel
We have several domestic housing estates within a 10KM radius from the factory. These estate consume pure single phase loads. Lights, fans, tv, mobile phone. Very basic living. Currently, the loads are supported by diesel generator.
We are considering eliminating the remote diesel generator to save costs. One of these estates is 6KM away and the load is 7KVA all single phase. Approx 30amps if using 230volts.
Is there any issue with sizing a simple 2 core cable (proposed 2 * 35mm2 aluminium cores) and running it underground (steel tape armoured) from factory to remote estate; at factory, have a step up transformer (to 1000volts) that can convert the 1 phase load and balance it across 3 phases for supply side; and lastly a single phase step down transformer at remote estate?
Or it is only advisable to run a 3 phase cable between the 2 sites and then distribute the loads as best possible between different houses. The cost of running 2 cores single phase is of course cheaper.
If the cable is direct buried 1 foot below the ground, is there any recommend material for backfill?
Really appreciate any help.
Prashant Patel