Czy wolisz polską wersję strony elektroda?
Nie, dziękuję Przekieruj mnie tamElektronik2013 wrote:Do you know how much it costs at PGE to increase the connection power by 6kW if it is a flat and the wires are already there, there is also a three-phase access to the connection point.
Elektronik2013 wrote:Security and the meter are not my property so I don't know how the costs are calculated here
elpapiotr wrote:Yeah, is it possible, only or the right one?![]()
karolark wrote:don't you think that it will be done for PLN 400?
Elektronik2013 wrote:Direct this question to the electrician who will do it as well.That is why I am asking here how much it will all be. The costs in a new home are different than in an apartment.
michcio wrote:16A pre-meter is not enough, because this is how much is installed in the socket circuits, and where is the security grading? There should be at least 20A ahead of the meter.
kkas12 wrote:Why not 25A ???
Elektronik2013 wrote:First, apply for the conditions for increasing the connection capacity to your energy operator. I propose to increase the power to 14 kW. You will then have 3x25A security. You will have the cost of connection as in the operator's price list + VAT. Unfortunately, you will have to finance the rest of the installation additionally. In any case, you have a long way to go in changing your power. I change my power supply from single-phase to three-phase and it has been going on since the beginning of September. The deadline for connection in the contract is until the end of June 2015.That is why I am asking here how much it will all be.
Elektronik2013 wrote:In my case, all that is needed is a meter replacement and new security measures.
Elektronik2013 wrote:Hello. In the apartment I have a connection power of 5kW, protection 25A. In my case, all that is needed is meter replacement and new security measures. Thank you in advance for your answer and I wish you a happy holiday.
kkas12 wrote:Let him spread the load. You won't spill anything from phase to phase. So what if there is 11kW in a pile.A person pushing the value of the pre-meter protection with a value of less than 25A (no matter if it is one or three phases) does not know what he is saying. And you will not avoid replacing the Wlz. So do not wipe your ass with glass.
TL;DR: Boosting an apartment supply from 1-phase 5 kW to 3-phase 11 kW typically costs about PLN 350 for the connection fee alone (58.38 PLN/kW) [Elektroda, Elektronik2013, post #14257004] “Meter exchange is on the operator’s dime” [Elektroda, zbich70, post #14257036] Expect extra PLN 1 000-3 000 for wiring and inspection.
Why it matters: Under-sized protection trips, while a balanced 3-phase setup sustains modern 3 kW appliances safely.
• PGE capacity-increase fee (Group IV): 58.38 PLN / kW [PGE Tariff 2015; Elektroda, #14257004] • Recommended main fuse for flats: 3 × 25 A ≈ 17.25 kW [Elektroda, kkas12, post #14257800] • 4 mm² Cu cable: safe load ≈ 25 A per phase, ≤ 30 m run [IEC 60364-5-52] • Meter replacement paid by operator; customer funds in-house works [Elektroda, zbich70, post #14257036] • Typical electrician + materials for WLZ & board: PLN 1 000–3 000 [Market Rates 2023]