Hello.
As I progress, I can report on what will result from my intentions.
I have a plot of land on which I built a farm building. I connected electricity to it (in accordance with all recommendations, regulations, contracts, etc., but during construction, ultimately to the "utility building").
Electricity flows to the building (based on all the documents required by PGE) at the C11 tariff (because this must be the case in the case of an "outbuilding"; PGE does not provide a different tariff here, as I was told by PGE).
The development plan does not provide for buildings other than single-family (house), utility/services, farm (anticipating the question - I was also thinking of turning it into a "recreation building" or "summer" - it is not possible, and I am not a farmer - farm).
I have the main box from which the "utility building" is connected at the border (ready, collected, sales contract in progress, electricity - great).
The construction has been completed, inventoried and marked on maps as completed.
The C11 tariff has been - because it has to be - the "utility building" C11.
Of course, there is no business or other activity (companies, etc.) conducted in the building.
Despite the completion of construction, the building looks like it is still under construction (no plasters), but it has windows, doors, a roof, etc., so the farm building does not need to be covered with marble.
The installation (received) is in the outbuilding (a couple of light sockets). The electricity is flowing, everything is fine, PGE has approved the contract for C11, a PGE technician has connected the meter.
Between the time of construction and the contract, a sheet metal garage (tin garage) was built.
And here we start the question.
Is it possible to change the contract from C11 to G11 on the basis of this sheet metal piece due to the desire to connect/switch the power supply not to the "outbuilding" (C11), but to the sheet metal man’s garage (G11)?
I have just received (another) raise, so "theoretically" I can terminate the contract sooner and possibly sign it again later (hopefully at G11). No problem on my end.
The question is how to deal with it so as not to go to consumer rights ombudsmen, etc....
I know that it is possible to arrange it from PGE’s side so that they issue a contract.
How can I argue for the document so that a possible technician who reconnects the meter, on G11, to the "garage" through the switchboard (internal, on my plot, in the outbuilding) does not accidentally find that construction is taking place on the plot and he will withdraw the contract because, for example, he will say "there is construction going on here and there must be a construction tariff, and besides, there is an outbuilding here and that’s it."
In case of doubts (questions), if anyone would like to provide a specific answer or advice from their own experience, I will stay in touch.
If an answer is not possible, please send me a private message.
Tomorrow, Friday, March 4, 2020, I’m going to PGE anyway to ask, but you can assume how it might end at the supplier’s office...
I will try to publish the official response in a short form for further discussion.
As I progress, I can report on what will result from my intentions.
I have a plot of land on which I built a farm building. I connected electricity to it (in accordance with all recommendations, regulations, contracts, etc., but during construction, ultimately to the "utility building").
Electricity flows to the building (based on all the documents required by PGE) at the C11 tariff (because this must be the case in the case of an "outbuilding"; PGE does not provide a different tariff here, as I was told by PGE).
The development plan does not provide for buildings other than single-family (house), utility/services, farm (anticipating the question - I was also thinking of turning it into a "recreation building" or "summer" - it is not possible, and I am not a farmer - farm).
I have the main box from which the "utility building" is connected at the border (ready, collected, sales contract in progress, electricity - great).
The construction has been completed, inventoried and marked on maps as completed.
The C11 tariff has been - because it has to be - the "utility building" C11.
Of course, there is no business or other activity (companies, etc.) conducted in the building.
Despite the completion of construction, the building looks like it is still under construction (no plasters), but it has windows, doors, a roof, etc., so the farm building does not need to be covered with marble.
The installation (received) is in the outbuilding (a couple of light sockets). The electricity is flowing, everything is fine, PGE has approved the contract for C11, a PGE technician has connected the meter.
Between the time of construction and the contract, a sheet metal garage (tin garage) was built.
And here we start the question.
Is it possible to change the contract from C11 to G11 on the basis of this sheet metal piece due to the desire to connect/switch the power supply not to the "outbuilding" (C11), but to the sheet metal man’s garage (G11)?
I have just received (another) raise, so "theoretically" I can terminate the contract sooner and possibly sign it again later (hopefully at G11). No problem on my end.
The question is how to deal with it so as not to go to consumer rights ombudsmen, etc....
I know that it is possible to arrange it from PGE’s side so that they issue a contract.
How can I argue for the document so that a possible technician who reconnects the meter, on G11, to the "garage" through the switchboard (internal, on my plot, in the outbuilding) does not accidentally find that construction is taking place on the plot and he will withdraw the contract because, for example, he will say "there is construction going on here and there must be a construction tariff, and besides, there is an outbuilding here and that’s it."
In case of doubts (questions), if anyone would like to provide a specific answer or advice from their own experience, I will stay in touch.
If an answer is not possible, please send me a private message.
Tomorrow, Friday, March 4, 2020, I’m going to PGE anyway to ask, but you can assume how it might end at the supplier’s office...
I will try to publish the official response in a short form for further discussion.