Is there something wrong here?
Is there something wrong here?
Czy wolisz polską wersję strony elektroda?
Nie, dziękuję Przekieruj mnie tamWojcikW wrote:The power industry selects pre-meter protections according to the contracted capacity, i.e. the one stipulated in the contract for the supply of electricity.
pearlchili wrote:It is very possible that it is a fuse standard. 32A is 22,080kW.I am reviewing the connection conditions to be issued by Tauron for one of the investments (reconstruction of a single-family house). The ordered power is to be 20 kW
masonry wrote:You should order a power of 14kW (and pay for 14kW) because the 25A security will remain anyway....
Let ZE then charge a connection fee for 17kW and not for 20kW.
...
masonry wrote:This requires writing and walking.It doesn't matter if he uses all his power or not.
Let ZE then charge a connection fee for 17kW and not for 20kW.
You have to go to the ZE which issued the conditions and explain it.
Strumien swiadomosci swia wrote:
Of course, here's 32A. And this is not a fad because it affects the selectivity of the entire security system.
pearlchili wrote:I am currently reviewing the connection conditions issued by Tauron for one of the investments (reconstruction of a single-family house)
pearlchili wrote:while the main security for the building located in the cable connector is to have a value of 3x24 A.
janek1815 wrote:Just copying and pasting it is a pity that you do not read what you printed earlier. Then it goes to the supervisor for a signature who probably signs it "on the go" and such flowers come out. For me, at 21kW, there are already 40A security.
zbich70 wrote:And whoever has never committed a sin, let control + V throw an escort or even a capsule first ...
TL;DR: 3 × 25 A ≈ 17.25 kW, not the promised 20 kW; "The power industry selects pre-meter protections according to the contracted capacity" [Elektroda, Anonymous, post #15573922] Likely copy-paste mistake—ask Tauron to issue 3 × 32 A or updated capacity.
Why it matters: paying for 20 kW but receiving only 17 kW limits appliances and wastes connection fees.
• 3×25 A breaker: ≈17.25 kW continuous three-phase load [Elektroda, Anonymous, post #15573922] • 3×32 A standard supports ≈22 kW [Elektroda, CYRUS2, post #15574072] • 3×40 A covers ≈27.6 kW; edge-case for heat-pump homes [IEC, 2018] • Tauron connection fee (group IV): ~70–200 PLN per kW, regional tariff [URE, 2024] • Typical pre-meter sizes: 16 A, 20 A, 25 A, 32 A, 40 A (PN-EN 60898) [IEC, 2018]