Only this application is submitted as a prosumer up to 50kW in Energa Link plus of course all the documents mentioned in this application.
I sent everything by e-mail.
Czy wolisz polską wersję strony elektroda?
Nie, dziękuję Przekieruj mnie tamTAGBA wrote:I reply to PW " Hi,
I wanted to ask you about this diagram that you showed for the energy of PV installations.
Did they accept him and make decisions about joining? Did you have to change something? Is this form ok?
And an additional question, how did you draw this schema? Any convenient tool?
Thanks
Paul "
I am attaching the current diagram, which I have submitted to Energa Operator and which has been approved and issued the permit.
Drawn in AutoCad.
Important note. It is best to call energy or look at the contract and the data of the object on the application as well as in the drawing should be identical to the contract. Even if it is not covered with reality.
I additionally attach a file in the .dwg version
Z1mmy wrote:1 YES, the protectors should be in front of, what sense they have for, as lightning is the main thing, the disconnector will cut off the flow and will not go to the protector.
Janusz_kk wrote:Z1mmy wrote:1 YES, the protectors should be in front of, what sense they have for, as lightning is the main thing, the disconnector will cut off the flow and will not go to the protector.
But when the protector falls, you will replace it under voltage or at night
two, the lightning pulse is probably too short to blow the fuse, so the circuit breaker behind the disconnection fuse still protects.
Z1mmy wrote:
Not. Because Solar Edge, as in the diagram we are talking about, is based on power optimizers that have safe DC functions. Which means that when you turn off the inverter, you have 1V for each panel up to a maximum of 50 panels in a string, i.e. 50V DC. You can disconnect and replace the protector, fuses etc. in full sun.
In a kalsic installation, yes. You have to either cover the panels or do it when there is no sun.
TAGBA wrote:What's happening with the tension? The inverter lets go of the protective ground?
Misiorrr wrote:OK thanks. so if I sign and write the address, it will be enough? will they accept without a stamp?
comer3 wrote:Hello,
(it will be Fronius, and from what I read it cannot work in the TT network).
![]()
Z1mmy wrote:You have to either cover the panels or do it when there is no sun.
TL;DR: 8-day grid-approval turnaround has been reported; “SEP is enough” [Elektroda, mirex1960, post #18186491] Follow the 30-day legal window and use a single-line diagram if your DSO still asks for it [Elektroda, comer3, post #18723220]
Why it matters: Correct paperwork and protection save weeks and prevent costly rework.
• Utility response time: 8–18 days reported, legal max = 30 days [Elektroda, comer3 #18723220; wello #18725777]. • Fuse-links on DC side required only for ≥2 parallel strings [Elektroda, noja102 #18187232]. • Target earth resistance ≤ 10 Ω; connect with ≥ 6 mm² Cu equipotential lead [Elektroda, tyqva #19519129; IEC 60364-5-54]. • Max string voltage SolarEdge: 900 V DC, 750 V nominal [Elektroda, 04.21 #19003679]. • Type T1 + T2 SPD recommended when building has external LPS [IEC 62305-3].