Recently, when I wrote it down, I had these parameters entered, it was just in the SMA inverter
but also look for the declaration of settings of this inverter in Polish
Czy wolisz polską wersję strony elektroda?
Nie, dziękuję Przekieruj mnie tamsnycesz wrote:Good day.
I do not want to start a new topic, so I will ask a question here. A sales representative of a company was at my place and offered a PV installation. What surprised me, (if the nomenclature is wrong, sorry) the lightning protection / additional grounding of the panels is done additionally. And from what you explained, they drag yellow-green 16mm2 from the panels to the DC switchboard with DC cables and spread to other elements of the system.
Friends have, for example, a separate cable to the ground and stuck pins? How is it legally regulated?
Thank you and best regards.
snycesz wrote:This is normal practice. You just have to be very careful and pay special attention to the cross-section of the cable to the socket. Often, power sockets are connected with a 2.5 mm cable or even with a four-wire installation. Simplifying a lot, 6kW to 2.5mm2 is theoretically ok, but the question of line length and voltage drop remains. You have to analyze and just plug inThanks for the quick reply. I will add this curiosity because I forgot about it in the morning. the gentleman suggested that it was similar to the cable from the AC switchboard to the power socket in the garage. Because I have the main switchgear in another part of the house where access is HUGE difficult.
Merio186 wrote:snycesz wrote:Good day.
I do not want to start a new topic, so I will ask a question here. A sales representative of a company was at my place and offered a PV installation. What surprised me, (if the nomenclature is wrong, sorry) the lightning protection / additional grounding of the panels is done additionally. And from what you explained, they drag yellow-green 16mm2 from the panels to the DC switchboard with DC cables and spread to other elements of the system.
Friends have, for example, a separate cable to the ground and stuck pins? How is it legally regulated?
Thank you and best regards.
Perhaps I will stick a stick into an anthill, but I think that when making a PV installation, the earth electrode in the building should be verified. If it is not there, it should be done. And here the real fairy tale begins, because making a real earth electrode costs both material and work. And it is good to inform the customer that the price of the earth electrode will be additional because it is impossible to measure how many pins or hoops will go to the earth electrode.
It makes no sense to dwell on the earth cross-section or preliminary measurements to determine the resistivity and predict the amount of material. During the valuation, there is no electrician in the warehouse, and the cross-section of the land is so diverse that either the valuation is made with a large margin or the truth is told - payable additionally.
But if the customer does not agree, how to put into use an endless installation?
The answer to the specific question and the rope. If you have a lightning rod on the roof and the separation distances are kept, then pulling the line to the GSW is correct in my opinion. If you do not have separation distances, it is a mistake to enter the house with the ground wire.
04.21 wrote:There have been three fires in single-family houses with PV installations in my area recently, many people have asked me if they are so emergency.
Z1mmy wrote:briefly answering:
I am attaching a sample image for the installation that I make for the client.
1 YES, the protectors should be in front of, what sense they have for, as lightning is the main thing, the disconnector will cut off the flow and will not go to the protector.
2 It makes no sense 2. Unless there are several parallel strings, then they should be used to cut off the reverse currents in the event of a short circuit on the panel if it breaks.
As a rule, the arresters and all PE should be connected to the main equalization rail and this one to the property's efficient earth electrode. If this does not exist, it should be made and measured. There are no regulations on resistance for the earth electrode, but the adopted rules are
TL;DR: 8-day grid-approval turnaround has been reported; “SEP is enough” [Elektroda, mirex1960, post #18186491] Follow the 30-day legal window and use a single-line diagram if your DSO still asks for it [Elektroda, comer3, post #18723220]
Why it matters: Correct paperwork and protection save weeks and prevent costly rework.
• Utility response time: 8–18 days reported, legal max = 30 days [Elektroda, comer3 #18723220; wello #18725777]. • Fuse-links on DC side required only for ≥2 parallel strings [Elektroda, noja102 #18187232]. • Target earth resistance ≤ 10 Ω; connect with ≥ 6 mm² Cu equipotential lead [Elektroda, tyqva #19519129; IEC 60364-5-54]. • Max string voltage SolarEdge: 900 V DC, 750 V nominal [Elektroda, 04.21 #19003679]. • Type T1 + T2 SPD recommended when building has external LPS [IEC 62305-3].